PROJECT PLANNER/ SCHEDULER
PROFESSIONAL SUMMARY
6 years’ experience using Primavera P6 and Microsoft Project in Project controls, planning and scheduling. Extensive experience in medium and high profile EPC Projects. Roles includes but not limited to building schedule from start to finish. Proficient in schedule development, progress monitoring, report and forecasting, resource allocation, earned value analysis, critical path analysis and baseline measurement. Exceptional communication skills, written and oral for effective collaboration with planning, design and management. Strong analytical skills in analyzing all aspects of the schedule cost.
EDUCATION
Zertifikat Deutsch, 2008 Goethe Institute, Lagos, Nigeria (German Language School)
BSc. Computer Science, Olabisi Onabanjo University, Nigeria
Skills
Primavera P6
Microsoft Project, Word, Excel, PowerPoint and Outlook.
Mind Genius
PROFESSIONAL EXPERIENCE
Plant Engineering Services Dec 2012-Jan 2013
BP South Houston Green Power
TAR Scheduler (P6 ver 7.0)
Responsibilities:
• Read through for completeness. Get with operations or Turnaround Management Team on items found that need to be added or deleted.
• Review work orders with appropriate parties to ensure that work orders are complete and the scope clearly understood
• Ensure all inspection requirements are resourced
• Work closely with the Material Coordinator to ensure the purchase and delivery of these materials meet the T/A milestones.
• Daily schedule updates.
• Attend turnaround planning team meetings and present planning and pre – turnaround status concerns. Take meeting minutes and maintain an action items list.
• Work with Turnaround Coordinator to develop Pre TAR activities
• Input work orders into the turnaround data base and continually update against P6, and the work order list.
• Identify maintenance capital work and write the work order numbers. E.t.c
Henkels & Mccoy (H&M) Aug-October 2012
Warranty Campaign-Bearing shaft replacement
Project Scheduler (Primavera P6 ver 6.0 & MS Project 2010)
Responsibilitie:
• Created overall project schedule with resource loading.
• Created overall project budget with information given. Include time & expenses for site teams, time for project manager, travel expense for PM site visits, tooling, and other miscellaneous charges.
• Created daily status report which includes work completed on that day, list of personnel on site, any safety issues that arose (if any), any special issue or situations that needed to be addressed and the projected work for the following day.
• Created weekly campaign budget update for every week of the campaign. Breakout labor costs, personal expenses tooling charges, etc. for the first week of the campaign.
Greka Energy Feb. 2010-June 2012
Project Scheduler (Primavera P6 ver 6.2 MS Project 2007&2010)
Worked on Rincon Oil field drilling project
Responsibilities:
• Reviewed with project management and issue baseline schedule
• Reviewed scope and agree with Project Business Manager/Project Controls Manager the Work Breakdown Structure.
• Developed engineering schedule taking into account priorities for vendor packages and early construction with the Project Technical Director.
• Ensured that the engineering schedule/document register is compatible with the procurement, construction and sail-away requirements.
• Developed detailed deliverables schedule from the engineering schedule for increased engineering scope and schedule visibility
• Developed overall PMT and engineering man-hour distribution over the project duration using approved man-hour budget.
• Verify that the man-hours spent on discipline activities are booked against activity codes for accurate reporting and project control.
• Define and optimize critical paths, perform total float analysis and notify project management status of critical activities and schedule risks.
• Conducted a what-if scenarios, recovery plans, contingency planning and schedule compression techniques.
• Issued 2-week look-ahead schedules and review with managers and lead personnel.
• Developed Level 1, 2, 3, and 4 project schedules, as applicable, to include engineering, procurement, construction, commissioning and installation.
• Review scope and agree with Project Business Manager/Project Controls Manager the Work Breakdown Structure.
• Incorporate construction, pre-commissioning, commissioning, load-out, installation and completion schedule inputs and progress into overall schedules as applicable. Review for conflicts with other elements of the schedule.
• Deliver plans and reports against fixed deadlines
• Report schedule updates, changes and potential constraints to senior management in regularly scheduled meetings
Julius Berger Nigeria Plc.
Construction Scheduler (Primavera P6 ver 6.0 & MS Project 2007)
Responsibilities:
Jan-Dec 2009
• Responsible for creating WBS, activities and milestones, maintaining Logic, Status update, CPM Analysis, Trending, and Forecasting.
• Evaluated durations against historical or similar projects by liaising with Engineering team and superintendents to determine work durations.
• Communicated project status report to project team and client via weekly meetings.
• Identify critical ...